Final Scope
Mayne Estates - Rezoning & Subdivision Plat
Village of Bergen Board of Trustees as Lead Agent
December 17, 2003
Introduction
This Final Scope has been prepared in accordance with Article 8
of the Environmental Conservation Law, the State Environmental Quality
Review Act, by the Board of Trustees of the Village of Bergen which
is acting as Lead Agency for the coordinated environmental review
of the pending action.
The Final Scope defines the content of the Draft Environmental
Impact Statement (DEIS) which must be prepared pursuant to the adoption
of a Positive Declaration by the Village Board at its meeting on
November 12, 2003. It is based on issues identified in the Positive
Declaration and statements made at a Public Scoping Session conducted
on December 4, 2003.
The first part of this Scope provides the narrative information
as required under 6 NYCRR Part 617.8(f).
Brief Description of Proposed Action
The proposed action includes rezoning of 54.4 acres of land and
subdivision and other approvals for Mayne Estates. The developer
proposes to develop lots within proposed R-1, R-2, R-3 and PUD zones
to include the construction of 61 single family residences, 23 single
family patio home residences, and 40 townhome units. The proposed
action will also involve the construction of roadways, sidewalks,
structures and extension of public utilities.
Potentially Significant Adverse Impacts
Based upon project plans, EAF, and input from the public and other
involved and interested agencies, the following potentially significant
impact areas have been identified:
1. Surface or groundwater quality or quantity
2. Noise levels
3. The community's sources of fuel or energy supply
4. Aesthetic resources
5. Agricultural land resources
6. Existing traffic patterns
Extent and Quality of Information Necessary to Address Issues
The Developer has submitted documentation with the EAF and preliminary
plat application dated 24 September 2003 which shall be incorporated
into a formal DEIS submission. The basic outline as submitted should
be updated to include the scope items contained herein. The DEIS
shall provide sufficient detail to reasonably assess proposed mitigation
measures and alternatives as described more fully below.
The Cover Sheet shall identify all required information contained
in SEQRA, Part 617.9(b)(3).
Initial Identification of Mitigation Measures and Alternatives
to be Considered
Potential mitigation measures which shall be evaluated in the DEIS
include:
1. Surface / Groundwater
Applicant shall evaluate stormwater management practices applicable
to this development, as compiled by NYSDEC in its Stormwater Management
Design Manual. Compare feasibility and costs related to each of
the following methods (initial construction and annual maintenance):
- a. stormwater ponds
- b. infiltration (discuss potential impacts to groundwater)
Assess impacts to the existing storm sewer system / drainage ways
and coordination of project mitigation alternatives with Village
drainage master plans:
- a. northerly to Munger Street / Rochester Street
------impact on wetland at intersection of Rochester Street / Buffalo
Road
------impact on wetland between CSX railroad and Rochester Street
- b. southerly to Apple Tree Avenue
2. Noise
Provide applicable OSHA guidelines for construction activities
within residential areas; confirm proposed typical operating procedures
to be utilized by construction forces
Propose a construction phasing plan, including typical hours of
operation
3. Community Resources - Fuel / Energy Supply
Evaluate capacity of the existing electrical system; cost to extend
services and the project's anticipated impact upon electric rates.
Provide additional information related to the extension of natural
gas; underlying assumptions on energy usage and demands.
Review potential allocation of energy usage between natural gas
and electric to minimize capacity and/or economic implications to
current municipal power customers (Village Electric Franchise Area).
4. Aesthetic
Proposed permanent conversion of rural farmstead and agricultural
appearance to suburban residential use could incorporate elements
that provide a "Village-like" feel (sidewalks, lighting,
landscaping); proposed elements; provide typical exterior facades
to facing streets and locations listed below.
Impact to existing views, evaluate from an "outside-in"
as well as an "inside-out" perspective, including photographic
documentation of the following locations:
- a. Public right-of-ways
- b. Munger Street residences looking south
- c. Village Park looking south and east
5. Agricultural Resources
Coordinate this proposal with policies outlined in the following
existing planning documents:
- a. Town / Village Comprehensive Plan
- b. Genesee County Smart Growth Plan
- c. Genesee County Agricultural Protection Plan
Anticipated use of any herbicides or pesticides related to the
project and their environmental impacts
6. Traffic Patterns
Impact on the following intersections:
- a. Buffalo Road (State Rte 33) and Parkview Drive
- b. Buffalo Road (State Rte 33) and Appletree Avenue
- c. Lake Avenue (State Rte 19) and Appletree Avenue
- d. Lake Avenue (State Rte 19) and Parkview Drive
Impact on routing of truck traffic through the development and
impact on the following intersections:
- a. Lake Avenue (State Rte 19) and Townline Road (State Rte 262)
- b. Lake Avenue (State Rte 19) and Rochester Street
- c. Buffalo Road (State Rte 33) and Lake Avenue (State Rte 19)
Incorporation of transportation improvements in conjunction with
any plans by Genesee County Highway Department for Rte 262 at the
westerly end of Parkview Drive and the Developer's plans for the
easterly end of Parkview Drive at Rte 33.
Evaluate potential pedestrian / vehicle conflicts and incorporation
of traffic calming measures and pedestrian facilities.
7. Community Growth
Alignment of community demographics with existing and future housing
needs. Review and update data contained in Chapter 3 of the Town
/ Village Comprehensive Plan (Population and Housing Trends and
Projections through 2000) and document how the development meets
the goals of the Comprehensive Plan.
Proposed phasing plan for the development of the PUD area; proposed
final PUD description; justification for townhomes and analysis
of need; alternative housing options considered by the developer
within the proposed PUD area in the event that the project is not
fully developed as townhomes; incorporate elements that provide
a "Village-like" feel (sidewalks, lighting, landscaping);
provide typical exterior facades to facing streets.
For further information:
Lead Agency: Village of Bergen
Address: 11 Buffalo Street
PO Box 100
Bergen, NY 14416
Contact Person: Tracy Jong, Village Administrator
|